请教:Project Evaluation
Your firm is contemplating the purchase of a new $925,000 computer-based order entry system. The system will be depreciated straight-line to zero over the project's five-year life, It will be worth $90,000 at the end of that time. You will save $360,000 before taxes per year in order processing costs, and you will be able to reduce working capital by $125,000 (this is a one-time reduction). If the tax rate is 35%, what is the IRR for this project?
谢谢各位高手
不好意思哦,读题的时候不仔细,没有看到关于working capital的说明。
因为新项目的存在,使得工程在开始时对working capital的需求减少了125000,所以第一年项目流出应该是-925000+125000=800000.最后一年项目结束时working capital 的需求恢复原状,所以最后一年项目的现金流入变为357250-125000=232250.其他年份没有变化。
-925000 298750 298750 298750 298750 357250 变成了
-800000 298750 298750 298750 298750 232250
我的计算器没有带回来,用excel函数求解,irr=23.8455%
凡是有working capital,初始时增加,在最后期减少。初始时减少,在最后期增加回来。
本题相当于year0减少了working capital投入,增加了净现金流125000,year5项目结束,项目的收益也结束,working capital增加了投入,减少了现金流125000。希望我说的比较清楚,呵呵。
[此贴子已经被作者于2009-1-17 23:21:31编辑过]